back to IMPACT homepage

Impact - EC research project

investigation of extreme flood processes and uncertainty

investigation of extreme flood processes and uncertainty

Work programme EC Research Project:
Project Reference No. EVG1-CT2001-00037

To receive e-mail updates on project progress
Impact project team members only

WP 2: Breach Formation - Laboratory Modelling


1. Modelling Facilities
2. Laboratory Data Collection
3. Test Programme


1. Modelling Facilities

A large flume at HR Wallingford (UK) was modified to undertake the first of three series of laboratory test. The flume is approximately 50 * 10 m in dimension and is equipped with a number of pumps that allow over 1 m3/s to be pumped through the facility. A large volume of storage upstream of the test section allows for continued flow as breach formation through an embankment occurs. An automated control system was developed to control operation of the pumps so as to maintain a steady upstream water level for as long period as possible. A large pit at the lower end of the facility acts as a sediment trap before water is released into a re-circulating sump system.


Figure 1: Flood channel facility

Back to WP2


2. Laboratory Data Collection

Laboratory Data Collection
For Lab Tests 1-17, the following data has been collected:

1. Inflow into the flume (P6).
2. Water levels upstream and downstream of the built embankment (L1, L2, and L3).
3. Approach velocity (Upstream of the built embankment).
4. Pore water pressure in the built embankment (P1-P4).
5. Photos and videos for monitoring breach development.

Limited data was collected for tests 18 and 19, as these tests were primarily undertaken to provide our partners in Norway with information about piping behaviour in moraine embankments. Data from tests 20 to 22 is currently being analysed by UK University and will not be included in the numerical modelling programme. However, data from these tests will be available for further analysis in the future by interested modellers.

Back to WP2


3. Test programme

Nine laboratory tests out of the project programme total of 22 tests were undertaken in the U.K. at HR Wallingford during August-September 2002. This series of tests was based around Field Test #2 – the minimum cohesive, homogeneous embankment. Each embankment was built in the modelling flume (See Figure) from non-cohesive material, however, more than one grading of sediment was used along with different embankment geometry, breach location and time before failure (seepage effect). . This approach allows investigation of the extent to which varying these parameters affect the breach growth. The different sediment gradings used were:

1. Uniform grading with D50 = 0.70-0.90 mm
2. Uniform grading with D50 = 0.25 mm
3. Wide grading (4 types of sand were used) with D50 = 0.25 mm

[Note: Uniform grading = as steep a grading curve as possible, dependent upon sediment suppliers. Wide grading = combination of different materials to match the grading distribution observed in the field. All of these gradings were based upon a 1:10 direct scaling of field test sediments).
Table 1 and Figure 2 below provide details of each test:

Table 1: Details of Laboratory Tests 1-9

Lab. Test Description
Lab. Test Objective
Grading
Lab Test #1 Trial / test experiment Facility set-up / trial
1
Lab Test #2 Uniform grading with the same D50 as Field Test #2 Effect of sediment uniformity
2
Lab Test #3 Same as Lab Test #2 Assess repeatability of test
2
Lab Test #4 Same as Lab Test #2, breach initiation notch against abutment Assess effect of breach location
2
Lab Test #5 Replicate Field Test #2 Direct replication to field event
3
Lab Test #6 Vary geometry, different face slope (1:2 instead of 1:1.7) Assess effect of face slope
3
Lab Test #7 Vary geometry, different crest width (0.30 m instead of 0.2 m) Assess effect of crest width
3
Lab Test #8 Same geometry as Lab Test #2, Uniform grading with higher D50 Assess effect of sediment size
1
Lab Test #9 Same geometry as Lab Test #2, allowing seepage before failure Assess effet of seepage
3


Figure 2: Grading curves for laboratory tests 1-9

A further 13 tests were undertaken in 2003:
Tests 10 – 17 were based around Field Test #1 at a scale of 1:10 to the field test. Test 10-16 were built from clay; Test 17 was built from moraine (see graph above for grading curves). Table 2 and Figure 3 provide details of each test:

Table 2: Details of Laboratory Tests 10-17

Lab. Test Description
Lab. Test Objective
Lab Test #10 Replicate Field Test #1 Direct replication to field event
Lab Test #11 Same as Lab Test #10 Assess repeatability of test
Lab Test #12 Same as Lab Test #10 but compacted with half of the compaction effort used for that test Assess effect of compaction
Lab Test #13 Same as Lab Test #10 but at optimum moisture content (Partially failed) Assess effect of moisture content
Lab Test #14 Remains of Lab Test #13 but left overnight Assess effect of seepage
Lab Test #15 Vary geometry, different downstream face slope (1:1 instead of 1:2) Assess effect of downstream face slope
Lab Test #16 Vary geometry, different downstream face slope (1:3 instead of 1:2) Assess effect of downstream face slope
Lab Test #17 Same as Lab Test #10 but built from moraine
instead of clay.
Assess effect of construction material
ame geometry as # 10 with different material

Figure 3: Grading curves for laboratory tests 10-17

Tests #18 and 19 were undertaken in support of Field test # 5, whilst Tests 20-22 monitored the initiation and development of piping failures in samples of real embankment material. Table 3 provides details of each test: Figure 4 shows the grading curve used for tests 18-22.

Table 3: Details of Laboratory Tests 18-22

Lab. Test Description
Lab. Test Objective
Lab Test #18 Replicate initiation of piping for Field Test #5 Provide information about
the pipe formation to assist in
development of the field test
failure mechanism
Lab Test #19 Same as Lab Test #18 Assess repeatability of the
test
Lab Test #20 Material brought from an UK flood embankment. Samples were 1m (W) x 1m (L) x 0.8m (D)
Monitor piping initiation and
development
Lab Test #21
Lab Test #22


Figure 4: Grading curves for laboratory tests 18-22



back to WP2
back to Top