back to IMPACT homepage

Impact - EC research project

investigation of extreme flood processes and uncertainty

investigation of extreme flood processes and uncertainty

Work programme EC Research Project:
Project Reference No. EVG1-CT2001-00037

To receive e-mail updates on project progress
Impact project team members only

WP 2: Breach Formation - Large scale field test


1. Field Test Program
2. Location
3. Description of the site
4. Data collection
5. Examples of use of the test-site
6. Norwegian National research Program
7. Contacts


1. Field test program

A total of five tests have been undertaken in Norway by Sweco GrÖner. These comprise:

- Field Test#1: The first field test (See Figure 1) was the ‘maximum cohesive’ embankment test that was undertaken in September 2002 (coinciding with the 2nd IMPACT workshop). The embankment was built mainly from clay and silt (D50 = 0.01 mm) with less than 15% sand and 25% of clay. The purpose of this test was to better understand breach formation and to identify the different failure mechanisms in homogeneous cohesive embankments failed by overtopping.

[Note: An initial data set for this field test was released to numerical modellers in August 2002 with modelling results presented at the 2nd IMPACT workshop in Mo i Rana. However, since the final test conditions proved to vary significantly from the initial theoretical conditions that were provided as a data set to modellers, a further data set with the actual field test conditions was released in February 2003. (See numerical modelling programme below for detailed info.). This permitted modellers to undertake modelling runs that can be compared directly against the field data.]


Figure 1: Geometry of Field Test #1

Page:1 03/03/04
-Field Test#2: The second field test (See Figure 2) was the ¡®minimum cohesive¡¯ embankment test (Field Test #2) that was undertaken in October 2002. The embankment was built mainly from non-cohesive materials (D50˜5 mm) with less than 5 % fines.The purpose of this test was to better understand breach formation and to identify the different failure mechanisms in homogeneous non-cohesive embankments failed by overtopping and also to assess /inspect the effect of seepage on the breach formation processes.

[Note: An initial data set for this test was also released in August 2002 to numerical modellers and the modelling results were presented in the 2nd IMPACT workshop in Mo i Rana. As with the first test case, actual test conditions also varied significantly from the target conditions hence a further data set with the actual field test conditions was released for simulation (See numerical modelling programme below for more info)].


Figure 2: Geometry of Field Test #2


- Field Test#3: The third field test was built as shown in Figure 3 in August 2003. The upstream and downstream shoulders were built from rock fill with a central moraine core. The purpose of this test was to better understand breach formation and to identify the different failure mechanisms in composite embankments failed by< overtopping. Numerical modellers will be asked to run at least one ‘blind’ and one ‘aware’ run with the data set of this test.


Figure 3: Geometry of Field Test #3

[Note: This field test was originally scheduled for 2002 but due to poor weather conditions in Norway in autumn 2002 it was delayed until summer 2003]

- Field Test#4: The fourth field test was built as shown in Figure 4 in September 2003. The upstream and downstream shoulders were built from rock fill with a central moraine core. The purpose of this test was to better understand breach formation and to identify the different failure mechanisms in composite embankments failed by piping. Two triggering mechanisms were used in this test case. Trigger mechanism #1 was a pipe perforated at the top and had the bottom half removed with the last part of it solid. The pipe was filled and surrounded by sand. The second mechanism was similar to the first one but with the sand fill extending from the bottom of the dam to the top. Trigger mechanism #1 did not appeared to work so failure occurred using Trigger mechanism #2.

As with each of the field tests, numerical modellers will be invited to run at least one ‘blind’ and one ‘aware’ run with the field data sets.



Figure 4: Geometry of Field Test # 4


- Field Test #5: The fifth field test was built as shown in Figure 5 in October 2003. The purpose of this test was to better understand breach formation and to identify the different failure mechanisms in homogeneous embankments failed by piping. Only one trigger mechanism was used in this test which was similar to the first mechanisms used in test #4. As with each of the field tests, numerical modellers will be invited to run at least one ‘blind’ and one ‘aware’ run with the field data sets.



Figure 5: Geometry of Field Test #5

Back to WP2

2. Location

A test site has been established in a river valley downstream of Lake Røssvatnet, the second largest reservoir in Norway. The test-site is situated in Northern Norway (See map). The reservoir belongs to SWECO, one of the IMPACT project partners.

Back to WP2

3. Description of the site

The test-site is in rock canyon. The site has been carefully prepared in order to prevent any leakage under or at the sides of the test-dams. A sill made of concrete has been built at the downstream side of the site. This sill is horizontal and is used as reference for construction of test-dams (See photo). A weir (See photo) for measuring of leakage through the test-dam has been built.

500 meters upstream of the test is the dam of Lake Røssvatnet. (See map , See photo) Large-scale test dams up to 6 meters high and 36 meter (See photo) long can be built across the river valley and then subjected to heavy flood flows as water is released in a controlled fashion from Lake Røssvatnet via the Røssvassdammen (See photo). Since the test site is upstream of a lake and a further reservoir, discharge flows can be controlled and contained, without risk of major flooding (See photo).

The gates at the dam of Lake Røssvatnet have recently been renewed and are easily operated so that exact amount of water may be released during the tests. People from Sweco SF operate the gates during the field tests.

Back to WP2

4. Data collection

A wide range of data can be collected for each test, including water levels, water-velocities, and flows. Several staff-gauges upstream and downstream of the test-site have been calibrated to facilitate the measurement of discharge. Pressure-sensors are used to monitor the pore-pressures in the dam. Specially designed sensors might be buried in the body of the dam in the cases of breach-testing, indicate when movement occurs and hence provide a profile of the time varying breach development through the dam. In this way actual dambreak data can be collected 'on the spot' for later use in model development and verification.

Back to WP2

5. Examples of use of the test-site

The site offers a rare facility to undertake tests at large scale, prototype scale or even larger than prototype scale, depending upon the particular scenario being tested. Water stored behind the test dam can reach approximately 90,000m3. (See Reservoir Capacity curve ) Combined with releases from the Røssvatnet Dam of up to 450m3/s, this provides the test site with enormous water potential with which to test dam or embankment behaviour. Not only breaching tests can be do, but also different other type of test e.g. test of stability, test of monitoring equipment for dams

In 2001 the first test of a 6-meter high dam was made (See photo , See photo). The objective of that test was to investigate the stability of a test-dam exposed to heavy leakage and to learn about the breaching mechanism.

A series of experiments has been made in 2002 partly within IMPACT, partly within the Norwegian Dam Safety test-program.

The first (cohesive - clay) test dam was breached in September and timed in conjunction with an International workshop on the project (See photo , See photo).

A series of test was made on the second (non-cohesive) dam:

6. Norwegian National research Program

Norway is running a dam safety project at the field test site. This project is co-ordinated by EBL Kompetanse, The Norwegian Electricity Industry Association EBL. A national working group/consortium is formed of three of the leading consulting Company in Norway: SWECO Gröner AS, Norconsult AS, Norwegian Geotechnical Institute (NGI) and the Norwegian University for Science and Technology(NTNU)

Back to WP2

7. Contacts

If you are interested in more information about the test-site and the possibilities test your own dams or embankments or more information about the Norwegian project, you can contact:

Kjetil Arne Vaskinn, SWECO Gröner AS, Member of the steering group and co-ordinator for the Norwegian part of IMPACT
E-mail: kjetil.vaskinn@sweco.no
Phone: +47 73990200 or +47 93058575

or

Aslak Løvoll, Norconsult AS
Email: alo@norconsult.no
Phone: +47 67571213

or

Tore Valstad, NGI
Email: tva@ngi.no
Phone: +47 22023090

back to WP2
back to Top