|
Combined Risk and Uncertainty
Objectives and Scope of Work
Careful consideration and use of the terms
‘risk’ and ‘uncertainty’ is required
when defining the objectives and scope of work. Text under
original project description of work (DOW) mixes these terms.
A clearer short summary would read:
“The objective of this work
package is to identify and emphasise the uncertainty associated
with the various components of the flood prediction process;
namely breach formation, flood routing and sediment transport.
The effect that uncertainty in each of these predictions has
on the overall flood prediction process will be demonstrated
through application to a real or virtual case study”.
Thus, the focus of this work under IMPACT
will be to:
- Investigate uncertainty within modelling
predictions for predicting breach formation, flood propagation
and sediment transport
- Demonstrate how uncertainty within each
of these modelling approaches may contribute towards overall
uncertainty within the prediction of specific conditions
(such as flood water level at a specific location)
- Consider the implications of uncertainty
in specific flood conditions (such as water level, time
of flood arrival etc.) for end users of the information
(such as emergency planners).
The scope of work under IMPACT does not allow
for an investigation of uncertainty in the impact of flooding
or in the assessment and management of flood risk. The assessment
of modelling uncertainty provides essential information upon
which a later assessment of the uncertainty in risk may be
developed through further research.
Remaining Programme of Work
The programme of work under IMPACT has deviated
significantly from its original outline programme (DOW) since
the issues involved are more complex than originally envisaged.
In order to achieve the objectives outlined above, it is now
necessary to focus on some specific stages of analysis, and
in doing so to clearly define limits as to the extent and
nature of analysis.
The proposed approach for analysis is
as follows:
- Analysis of individual model sensitivity to parameter
variation will be undertaken. This may include either simple
analysis of the effect of varying individual parameters
and / or the effect of varying parameter probability distribution
functions (pdf) – this where models can undertake
Monte Carlo analysis and parameters can be represented in
this way.
This analysis will permit an understanding of model performance
in relation to modelling parameters. It will demonstrate
the relative importance of various parameters to modelling
results.
The extent to which the analysis is undertaken will be left
to the (expert) judgement of the modellers such that all
parameters which are likely to have significant influence
on modelling predictions are analysed. Note that the choice
of pdf is also open to expert judgement, hence sensitivity
to assumed pdf may also be examined.
- When analysing parameter variation [1 above] consideration
should also be given to the difference between model parameter
uncertainty and model physics uncertainty. That is, how
well does the model represent the physical process? This
issue is far from simple and, in effect, is the process
through which model development is undertaken. Conclusions
for model improvement will be made and where possible, (subjective)
estimates as to how this might reduce uncertainty made.
- Demonstrating the combined effect of model uncertainty
will be undertaken through application of models to the
Tous and / or Lake Ha! Ha! case studies.
A probabilistic approach to combining uncertainties will
not be undertaken. A less rigorous, more subjective but
equally more practicable approach (within the IMPACT framework)
will be taken whereby central, upper and lower scenarios
will be estimated using the various models. This will require:
| a) |
Clear identification of a parameter
that is being investigated (e.g. water level at a
specific location; time of flood wave arrival etc) |
| b) |
Expert judgement as to how individual modelling
results might combine to give central, upper and lower
estimates |
Where time permits, further combinations may be assessed
to highlight combined model behaviour in more detail.
- Consideration will be given to the combined modelling
results to assess how potential uncertainty may influence
use by end users. Prior to undertaking steps 1-3 above,
it will be important to review who the key end users are,
and how they might use the modelling results. This will
influence the selection of modelling results under steps
1-3.
Annex 1: Key Issues & Challenges (Louvain Nov 2003)
The following points were noted during discussion
at the 3rd IMPACT workshop:
- Clarification of the scope of work on this topic under
IMPACT is needed. Perceptions both within and external to
the project vary significantly.
This statement should clarify the scope of work. Details
will also be posted to the web and the DOW updated in January
2004.
- Discussion upon methods of analysis focussed around two
approaches; a more rigorous mathematical approach versus
a less rigorous subjective approach.
The work required undertaking a rigorous mathematical
approach is extensive and requires specialist skills that
IMPACT team members do not necessarily have. The scope of
work proposed under IMPACT and the budget available does
not allow for this. It was concluded that a more subjective
approach would a) fit with the original scope and budget
of IMPACT and b) meet the requirements for many end users.
[In addition, the knowledge of pdfs for the so called ‘rigorous’
analysis does not exist. The ‘rigorous’ analysis
therefore requires subjective assumptions that may be disguised
in the presentation of the results which could be misleading
as to the true level of knowledge.]
- The subjective approach means selection (at minimum) of
scenarios representing an upper, lower and central estimate.
Selection of conditions to create these scenarios will require
expert judgement (hence subjectivity). Parameters and what
may be considered upper, lower and central will vary from
model to model, and modeller to modeller.
This approach does allow different modellers (breach
modellers particularly) to compare predictions for upper,
lower and central estimates. Variation may be a function
of judgement and / or uncertainty in the model representation
of the physical processes.
However, it is important to recognise that scenarios (i.e.
selected parameter values or distributions) need to be credible.
They are not necessarily limits or bounds of all possible
outcomes and they have no probabilistic interpretation (e.g.
confidence limits). By ‘credible’, it is suggested
that parameter values selected have or may have occurred
or may realistically be expected to occur.
- It is only realistic to consider uncertainty for a specific
parameter at a specific location. No attempt will be made
to assess uncertainty in multiple parameters simultaneously
for the entire modelled area.
- The focus on analysing model uncertainty means that issues
such as whether breach occurs or not, will not be considered.
Annex 2: Outline Programme of
Work
Step1: Identification of end users and
overall modelling parameters
HR to initiate. Other partners to contribute.
Identify likely end users for modelling outputs. Identify
probable parameters for end user use.
Conclude which parameter(s) will be studied in combined modelling
analysis
[End
Jan 2004]
Step 2: Data set for sensitivity analysis
Theme Leaders for WP2, 3 & 4 to select data sets (case
study or laboratory data) for sensitivity analysis of breach,
flood propagation and sediment transport models.
Theme leaders to confirm parameter(s) for comparison during
analysis (based upon 1 above)
[End
Feb 2004]
Step3: Undertake parameter sensitivity analysis
Theme leaders and other partners to undertake sensitivity
analysis for their respective models leading to a prediction
of upper, lower and central estimates.
Theme leaders to also review differences between results where
more than one model has been analysed for a specific function
(e.g. multiple breach model predictions)
Initial conclusions on modelling uncertainty produced
[End
Mar 2004]
Step4: Combined uncertainty analysis
Following review of Lake Ha! Ha! data, decision to be made
as to final case study or studies data.
Agreement on extent of run scenarios.
Analysis of case study data
Theme leader analysis of combined results
[to
be undertaken as part of overall case study application –
mid summer 2004]
Step5: Implications for End Users
HR to initiate. Other partners to contribute.
Discussion leading to key points and observations for presentation
at final workshop.
[Autumn
2004]
|
|